Representative Project Experience


The following projects are representative of contract work completed by Resource Environmental in 2007. Resource completed over 100 projects in 2007-below are just 15.


Project Scope of Work Contract Value
Boeing, Long
Beach
Abatement of below-grade asbestos transite piping from 100 acre site $50,000
Zoeter School,
Seal Beach
Abatement of asbestos, lead, mold, and other hazardous building materials from 30,000 sqft school building. Demolition and site-clear of buildings. Restoration of day care school building, including new exterior wall, lectrical, plumbing, HVAC system work. $600,000
Orange County
Sanitation District
Clean-up of asbestos and lead paint from occupied industrial buildings. $25,000
Longo Toyota, El
Monte
Abatement of asbestos pipe insulation $2,000
1880 Century
Park East,
Century City
Abatement of asbestos fireproofing from Lobby and Restaurant of occupied highrise
building. Scaffold deck "dance floor" was constructed in lobby from which abatement was completed while lobby remained fully operational. Work in Restaurant was completed from scaffold deck that we designed to hang from deck framing so that ceiling system could be saved.
$300,000
Nieblas School,
Fountain Valley
Abatement asbestos flooring, pipe insulation, below-grade transite piping and lead
ceramics from 50,000 sqft school site
$85,000
St. Mary's Church,
Palmdale
Abatement of asbestos, lead and other hazardous building materials from church.
Demolition and site clear of 10,000 sqft church.
$90,000
4th Street
Apartments, Santa
Monica
Selective abatement of asbestos drywall from occupied 25 unit apartment complex
as required for new pluming and HVAC work. Work completed in each unit while
tenant temporarily vacated apartment on a daily basis.
$90,000
Encino Plaza,
Encino
Spot abatement of asbestos spray applied fireproofing, construction of asbestos
containments and contractor-assist during elevator modification work.
$10,000
Cal State San
Bernardino,
Physical Sciences
Renovation
Abatement of asbestos flooring, spray-applied fireproofing, pipe insulation, transite
pipes, from 5 story, 45,000 sqft school building. Decontamination of toxic mold from
various locations.
$150,000
PG&E, Hinkley Abatement of various asbestos and lead materials from 30+ structures. $150,000
St. Mary's
Academy,
Inglewood
Abatement of asbestos ceiling, floor tile and pipe insulation from 50,000 sqft school
building.
$100,000
Pomona Catholic
High School
Emergency response abatement of asbestos flooring as required after flood. $1,800
Naval Base,
Ventura County
Abatement of lead painted building components from housing complex consisting of
72 buildings with 315 living units
$200,000
Chapman
University
Abatement of 1,000 lnft of asbestos pipe insulation $10,000